What is retention in construction? Definition, calculation, release, and accounting

What is retention in construction? Definition, calculation, release, and accounting


What is retention?

Retention is a percentage of each progress payment that a client holds back until the work is complete and any defects are fixed. It is also called retention money, retainage, or retained amounts, and in Arabic, خصم ضمان الأعمال or المبالغ المحتجزة.

A contractor submits a progress claim, the consultant certifies the value of the work done, and the client pays the certified amount minus the retention. The held-back money guarantees that the contractor will finish the job and repair defects, and it is paid out later, usually in one or two stages.

At a glance

Retention

Also called

Retention money, retainage, retained amounts, خصم ضمان الأعمال, محتجز ضمان الأعمال

Who holds it

The client or main contractor

Typical rate

5% to 10% of each progress payment, set in the contract

Purpose

Guarantee completion and cover defects

Released

At practical completion, after the defects period, or at final handover

Appears as

A receivable for the contractor, and a payable for the client

Retention here means retention money in contracts. It is not the same as customer retention, data retention, or retained earnings, which are different accounting and business terms.

Read also: Construction invoice template: the “why” behind the specialized invoice

Why does retention matter for contractors and clients?

Retention protects the client against unfinished or defective work, but it ties up the contractor’s cash for months or years. Both sides need to plan for it from the start.

  • For clients: it gives leverage to get snags fixed and the job finished, without chasing the contractor for refunds.
  • For contractors: wages, subcontractors, and suppliers are paid in full, while 5% to 10% of each claim is not received.
  • For cash flow: on a long project, retention can grow into a large balance that you must finance.
  • For tax: VAT and other taxes may fall due before the retention is paid, which adds to the cash strain.
  • For records: retained amounts need their own tracking, so they are not forgotten at the end of the project.

Because retention sits in receivables for a long time, track it separately in your aging report, so it does not hide inside overdue balances.

Read also: Cash flow statement: how does it work

How is retention calculated?

Retention equals the certified value of work multiplied by the retention rate, until any cap in the contract is reached. Many contracts cap the total at a percentage of the contract value, such as 5%.

Example:

The example below uses a contract of AED 2,000,000, a retention rate of 10% on each claim, and a cap of 5% of the contract value (AED 100,000). Amounts exclude VAT.

Progress claim

Certified work (AED)

10% rate (AED)

Retention held (AED)

Total retention (AED)

Claim 1

500,000

50,000

50,000

50,000

Claim 2

700,000

70,000

50,000

100,000

Claim 3

800,000

80,000

0

100,000

Total

2,000,000



100,000

100,000

In claim 2,

The rate would hold back AED 70,000, but only AED 50,000 remains under the cap, so the retention stops at AED 100,000.

The contractor receives AED 450,000 for claim 1, AED 650,000 for claim 2, and AED 800,000 for claim 3, a total of AED 1,900,000 before the retention is released.

What does a progress claim with retention look like?

A progress claim lists the work certified to date, then deducts the advance recovery and the retention, to reach the net amount payable. The sample below uses a first claim with a 10% advance recovery, excluding VAT.

Line

Amount (AED)

Notes

Contract value

2,000,000

Fixed in the contract

Work certified in this claim

500,000

Certified by the consultant

Less: advance payment recovery (10%)

(50,000)

Recovers the earlier advance

Less: retention (10%)

(50,000)

Held until release

Net payable before VAT

400,000

Cash due from the client

Retention held to date

50,000

Shown on every claim

Showing the retention held to date on every claim lets both sides check the balance as the project goes on and prevents disputes at the end.

Read also: Understanding accounting entries: a comprehensive guide with practical examples

When is retention released?

Retention is released when the contract says so, usually half at practical completion and the balance after the defects liability period ends. Some contracts release it all at final handover.

Stage

What happens

Typical release

Practical completion (taking over)

The works are complete, and the client takes possession

Often half of the retention

Defects liability period

The contractor fixes defects that appear, often for 12 months

Held until the period ends

Final handover or final certificate

The consultant confirms all defects are fixed

The remaining retention

Retention bond alternative

The contractor gives a bank guarantee instead of cash retention

Cash retention released against the guarantee

To get paid, the contractor requests the release, the consultant certifies it, and the client pays. Check the contract for exact stages, percentages, and time limits, as they vary between projects and client types.

What documents do you need to claim the release?

To claim release, you typically need the practical completion certificate, the defects clearance certificate, the final account, and the original invoices. Check the contract for the exact list and the deadline for submitting it.

  • The consultant’s certificate of practical completion, with its date.
  • The certificate confirming the defects period has ended, and defects are cleared.
  • A statement of the retention held, by claim, that matches your records.
  • A release request addressed to the client, with the amount and the contract clause.
  • Any bank guarantee or bond that the contract requires to be returned.

How does retention differ from advance recovery, performance bonds, and defects liability?

Retention is cash withheld from payments, a performance bond is a bank guarantee, and an advance is recovered from claims. Defects liability is the period of repair duty. They often appear together in one contract, so it helps to keep them apart.



Retention

Performance bond

Advance payment

What it is

Cash withheld from each claim

A bank guarantee, often 5% to 10% of the contract

Money paid to the contractor before work starts

Who provides it

The client holds the money

The contractor’s bank issues it

The client pays it

How it ends

Released in stages

Returned at final acceptance

Recovered from each claim

Accounting

Receivable or payable

Off-balance-sheet guarantee, with fees expensed

Advance liability or receivable until recovered

The defects liability period is not money at all: it is the time during which the contractor must repair defects. The retention is what the client holds while that period runs.

Read also: Construction progress billing under ZATCA e-invoicing: how to handle advance payments and retention

How do you account for retention?

The contractor records retention as a receivable, the client records it as a payable, and both clear it when the money is released. The same example shows both sides for claim 1, excluding VAT.

Event

Contractor

Client

Claim 1 certified (AED 500,000, retention 50,000)

Debit receivable 450,000 and retention receivable 50,000; credit contract revenue 500,000

Debit work in progress or cost 500,000; credit payable 450,000 and retention payable 50,000

Net amount paid

Debit bank 450,000; credit receivable 450,000

Debit payable 450,000; credit bank 450,000

Retention released (AED 100,000)

Debit bank 100,000; credit retention receivable 100,000

Debit retention payable 100,000; credit bank 100,000

Use a dedicated retention account so the balance can be tracked by project. Setting that up starts with your chart of accounts. Under revenue recognition rules for long contracts, the contractor may classify the retained amount as a receivable or a contract asset, so confirm the treatment with your accountant.

Read also: Difference between accounting entries in sale and purchase

Retention in the UAE and Saudi Arabia

VAT follows the value of the work, not the cash received, so plan for tax on the full certified amount. Check the treatment of retention with your tax adviser, because the rules differ by country and by the stage of the contract.

Topic

UAE

Saudi Arabia

Currency

AED

SAR

VAT on retention

Tax points for contracts with periodic payments follow Article 26: the earliest of the tax invoice, the due date on the invoice, or payment received. Advisers differ on whether VAT on retention falls due with the progress invoice or at release, so confirm with your tax adviser or the FTA

Wafeq’s guide summarizes ZATCA’s position: VAT is due on the full value of the works before retention, and releasing retention does not need a new VAT invoice

Tax invoice

Issue a tax invoice within 14 days of the date of supply

Issue an e-invoice for each progress bill through Fatoora

E-invoicing

E-invoicing is phased in from 2026 and 2027 by revenue band

Phase 2 e-invoicing applies by wave

Corrections

Use a credit note when the consultant adjusts a claim

Use an electronic credit note linked to the original invoice

For the UAE, see the guide to VAT invoice requirements in the UAE. For Saudi Arabia, the approved e-invoice template shows what a progress bill must contain.

Read also: Why is the Fatoora portal rejecting your invoices? Practical solutions for ZATCA integration errors

Common retention scenarios and what to do

What if the client delays the release?

Send a written release request with the certificate, follow up on the contract’s payment deadline, and record the overdue amount as a separate receivable. Check whether the contract allows interest or other remedies for late release.

What if defects appear during the defects period?

Fix them promptly and document the repair, because the client may use the retention to pay for repairs you do not complete. Photos and sign-off from the consultant protect your claim to the balance.

Can a bank guarantee replace cash retention?

Yes, many contracts let the contractor provide a retention bond or bank guarantee, so the client releases the cash while the guarantee stays in place. Guarantee fees are a cost, so compare them with the cost of financing the retained cash.

How do subcontractor retentions work?

A main contractor often applies retention to each subcontractor, while the client holds retention from the main contractor. Align the release dates so you are not required to pay subcontractors before you receive your own retention.

When a consultant rejects part of a claim after you have invoiced, issue a credit note, as explained in how to handle credit notes in KSA e-invoicing

Read also: How accounting software empowers business owners to master their finances

How do you record retention in Wafeq?

In Wafeq, you record retention directly on the invoice, track the retained amount in a dedicated retention account, and settle the balance later. Retention sits alongside advance payments and project tracking in the same invoice workflow.

[Wafeq UI: Invoice with a retention line, and the retention account balance by project. To be captured from a live construction organization.]

  • On the invoice: add the retention to the progress invoice, together with any advance recovery line.
  • Retention account: the retained amount is tracked in a dedicated retention account so you can see how much each client owes you.
  • Projects: assign projects to invoices, expenses, and supplier bills to see profitability per project.
  • Settlement: when the retention is released, settle the outstanding balance and apply the payment.

These features are described on Wafeq’s page for construction and contracting businesses. For Saudi Arabia, the progress billing guide explains how the retention deduction is handled in the e-invoice.

How should you track retention across projects?

Keep one retention balance per project and client, with the rate, cap, and release dates recorded at the start. Review the list monthly so no release date is missed.

  • Record the retention rate, cap, and release stages for each contract.
  • Show the retention held to date on every progress claim.
  • Review retention balances by project every month.
  • Diary the practical completion date and the end of the defects period.
  • Reconcile the retention account with the client’s records before each release request.

Common mistakes with retention

The most common mistakes are forgetting to track retention, applying the wrong rate or cap, treating VAT as deferred, and missing the release deadline. Each one is easy to prevent with a project-level routine.

Mistake

Fix

Retention not tracked separately

Use a dedicated retention account, reported by project

Wrong rate or cap

Check the contract for the rate, the cap, and release stages

Assuming VAT waits until release

Confirm the VAT treatment, and plan cash for tax on the full certified value

Missing the release request

Diary the practical completion and defects period dates

Releasing without a certificate

Release only against the consultant’s certificate

Defects not documented

Record each defect and its repair with dates and photos

Read also: UAE VAT guide: what every business needs to know

Retention is a simple idea with a long tail: a small percentage of every progress payment is held back, and it can stay out of your hands for a year or more. Know the rate, the cap, and the release stages in your contract, track the retained amount separately, and plan your cash and your VAT around it. Handled this way, retention protects the client without starving the contractor of cash, and it is paid out on time at the end of the project.

FAQs about retention

Is retention the same as a security deposit?

Not exactly: a deposit is paid upfront, while retention is withheld from progress payments and released after completion and the defects period. Both act as a guarantee.

What is a typical retention percentage?

Most contracts hold back 5% to 10% of each progress payment, often with a cap on the total, but the contract sets the exact figure. Always check the conditions of the contract.

Is retention an asset or a liability?

For the contractor, retention is a receivable or a contract asset, and for the client it is a payable owed to the contractor. Both are clear when the retention is released.

Is VAT due on retention when it is withheld?

VAT is based on the value of the work, so plan for tax on the full certified amount and confirm your country’s treatment. In Saudi Arabia, ZATCA treats retention as a deferral of cash, not a price reduction.

When is retention released?

It is released as the contract states, often half at practical completion and the rest after the defects liability period ends. A certificate from the consultant usually triggers payment.

What is the defects liability period?

It is the period after completion, often 12 months, when the contractor must fix defects at its own cost. The final part of the retention is usually held until it ends.

Can a bank guarantee replace cash retention?

Yes, if the contract allows, a retention bond or bank guarantee can replace cash retention, improving the contractor’s cash flow. The guarantee has a cost and an expiry date to manage.

What happens to retention if the contractor does not fix defects?

The client may use the retention to pay for repairs, within the rights the contract gives, and release only the remaining balance. Document defects and notices to avoid disputes.

Is retention the same as retained earnings?

No, retention is money withheld under a contract, while retained earnings are a company’s accumulated profits shown in equity. The terms look similar but belong to different parts of the accounts.

Know what each client still owes you, project by project.

Bill progress claims with retention and advance recovery, track retained amounts in a dedicated account, and settle them when released. Start a free trial and set up your first project today.

Start with Wafeq now for free

Related topics